Preview

critical path

Good Essays
Open Document
Open Document
543 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
critical path
Critical Path Analysis (CPA)
Critical Path Analysis: A project-management technique that lays out all the activities needed to complete a task, the time it will take to complete each activity and the relationships between the activities.
Sets out all the individual activities that make up a larger project.
Shows the order in which activities have to be undertaken.
Shows which activities can only take place once other activities have been completed.
Shows which activities can be undertaken simultaneously.
Shows when certain resources will be needed.
Once the Critical Path Analysis has been constructed, the business will be able to identify the Critical Path itself, which is the route on the Critical Path Analysis that has no spare times (float). This means that if there is a delay in any of the activities of the critical path, the whole project is going to be delayed unless the firm changes something to aid bringing the project back onto track. Some operations on the Critical Path Analysis may have some spare time, when this is the case the firm can afford to time some time in completing their project, so long as they do not exceed their spare time.
The minimum time in which a project can be completed is the total time taken across the critical path.
If a business has a project delayed, they can:
Check to see whether they have any spare time in any other parts of the project, if they do they can switch staff from one activity to another to try aid in catching up on the delayed activity.
They could also higher extra people to try help in catching up, though it will add to costs, it is essential as it helps in putting the project back on track and not being delayed.
Key Rules:

The CPA must always being and end with a ‘Node’
Nodes are numbered to represent what position they are in the activity, the Earliest Start Time (EST) of an activity, and also the Latest Finish Time (LFT).
In the CPA, there must be no crossings in activities
Each activity

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Powerful Essays

    MGT2 Task3

    • 5037 Words
    • 21 Pages

    Increase the project team size to catch up and speed up progress reducing potential for any further schedule…

    • 5037 Words
    • 21 Pages
    Powerful Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    If you are unable to complete it on time, others could reprioritise their others tasks in order to give you more time to complete it, or they may offer to let you delegate some of the work that needs to be completed so that you have less to do and can then complete the task on time.…

    • 821 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Lean Production

    • 2877 Words
    • 12 Pages

    One method used by Metov’s is critical path analysis (CPA). CPA is the process of planning the sequence of activities in a project in order to discover the most efficient and quickest way of completing it. Metov’s have recently been able to incorporate this technique due to recent advancement in the companies ICT system so that more advanced software which could run CPA could be utilised. There are many advantages to this technique. Metov’s constructed a CPA for setting up a new factory in Dover, in doing this they were able to work out the latest finish time was 19 weeks. This meant they were sure that two majors customers with orders worth £1million and £2million respectively would get there orders in time and this increased customer satisfaction. In addition CPA has helped with particular concentration on speed of delivery. This enabled less factory space to be wasted on storage of raw materials and more production to take place, which was of real benefit as the factory was already crowded. With increased speed of production comes an increased level of production which means they were able to sell more products and satisfy more orders/customers. CPA also assists in helping to control and review. Metov’s will be able to analyse CPA to monitor the progress against the original plan thus highlighting any delays and steps which could be taken to rectify a problem.…

    • 2877 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Project Management

    • 2565 Words
    • 9 Pages

    Everyone hates it, but one logical place to start is with overtime. If people work more hours, they can get more work done in the same amount of calendar time. Overtime may be the best option if you're close to the end of the project and just need a final push to get everything done on schedule. If you're toward the end of the project, you also may be able to issue comp time after the project is completed. If you're still early in the project, there are probably more effective strategies. This option may also have cost implications if you need to have contract resources work overtime..…

    • 2565 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    Week 5

    • 548 Words
    • 3 Pages

    With the information provided, the project will take 34 weeks to complete. The critical path is in red color.…

    • 548 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    1. When is the project estimated to be completed? How long will the project take?…

    • 280 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Project Crashing Using Cpm

    • 1143 Words
    • 5 Pages

    We can however reallocate resources from one facet of the project and use it to speed up an activity that is lagging behind OR we can all together allocate new resources to our ACTIVITIES IN CRITICAL PATH. However care must be taken that, if the resources should always be withdrawn from activities that have more SLACK . In Short for project crashing we have to concentrate our efforts on THE CRIRICAL PATH i.e whatever efforts we have to do in term of time , resources or budget will be done on the critical path and these things have to be taken out either from the non-critical activities having enough SLACK or new allocation should be made.…

    • 1143 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    Given the dimensions of the project and critical path of the project, what can be done to bring the project back on track?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays