Preview

Ms Project Lesson 3

Satisfactory Essays
Open Document
Open Document
298 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Ms Project Lesson 3
Review Questions

Name ____________________________

Answer the following questions (use MS Project help if necessary):
1) Define effort-driven?
a) Effort-driven scheduling extends or shortens the duration of a task to accommodate changes to resources but doesn't change the total work for the task.

2) Under what circumstances would you turn off effort driven scheduling?
a) When you do not want the duration of a certain task to change. If you have a four day review for everyone on the project, when you assign more resources to that task, the days decrease, this is when you do not want effort driven scheduling. You want it to stay at 4 days.

3) Use a real-world example of when you would make a task as a Fixed Duration type task?
a) A painter is assigned to paint the living room in 4 days which is 32 hours of work. The customer asks the painter to paint another room, but the painter can only work part time 50%. Enter 50%, the project keeps the duration fixed at 4 days and recalculates the work to be 16 hours.

4) What is the formula for calculating duration?
Work / Units = Duration

5) What are the eight preset work contours (hint: In the Task Usage view right click on a resource name an open the assignment information box) and what are the procedures in applying them to a resource on a task?
a) Flat
b) Back-loaded
c) Front-loaded
d) Double Peak
e) Early Peak
f) Late Peak
g) Bell
h) Turtle
i) To change the work contour for an assignment in either Task Usage View or the Resource Usage View, double-click an assignment to open the Assignment Information Dialog box and choose a contour from the Work Contour drop-down

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    The resource allocation for each activity for each week and the total weekly resource assignments are show…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    If one of these constraints was to change, then the other two would be immediately influenced. To ensure that these essential constraints do not become detrimental to the project our team must follow similar standards that completed subdivision projects have put in place. Cost and Time will be managed by monitoring project performance closely through an Earned Value Analysis.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    4) Refer to the figure. What is the slack time, in days, associated with activity D?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    2) What is resource leveling? When performing project planning activities, the manager will attempt to schedule certain tasks simultaneously. When more resources such as machines or people are needed than are available, or perhaps a specific person is needed in both tasks, the tasks will have to be rescheduled concurrently or even sequentially to manage the constraint. Project planning resource leveling is the process of resolving these conflicts. It can also be used to balance the workload of primary resources over the course of the project[s], usually at the expense of one of the traditional triple constraints (time, cost, scope).…

    • 511 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    2. Once the resource leveling is completed, the over allocated resources decrease from 4 to 2. The over allocated problems are design engineer and industrial engineer, with the greatest total slack for detailed marketing plan decreasing. In the end the project task changes in the duration period after resources leveling.…

    • 402 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    For targets to be realistic for work, a clear timetable is needed. If unable to complete in that time, negotiate for a bit longer this avoids any stress more than necessary. The benefit is the satisfaction of completing on target.…

    • 1226 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    In many cases, when we do not blame hard to be productive while we say that time goes fast and is the only culprit but we realize that we are truly wrong, so that productivity is not defined depending on the time we have pros and cons, but of how we distribute the time to be able to find in our business productivity.…

    • 587 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    E Alfonzo

    • 711 Words
    • 3 Pages

    Usage and availability of resources are major problem areas for project managers Attention to these areas in developing a project schedule can point out resource bottlenecks before the project begins. Project managers should understand the ramifications of failing to schedule resources. The results of resource scheduling are frequently significantly different from the results of the standard CPM method.…

    • 711 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Organizational Skills

    • 932 Words
    • 4 Pages

    Firstly, the project was broken down into manageable tasks and given a set amount of time to complete, thus creating a timeframe.…

    • 932 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Data Com

    • 698 Words
    • 3 Pages

    A periodic composite signal with a bandwidth of 2000 Hz is composed of two sine waves. The…

    • 698 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Giant Chart

    • 631 Words
    • 3 Pages

    Gantt charts have a variety of uses among construction professionals. Gantt charts must be used under the following circumstances:…

    • 631 Words
    • 3 Pages
    Good Essays
  • Good Essays

    - it means that wasteful motions, delay and uncertainty are to be minimized, and at the same time responsibility for specific tasks is to be assigned , thereby leaving the boss free to do what he only can do.…

    • 1049 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    How productive are you

    • 1836 Words
    • 8 Pages

    When we want to get more done, many of us simply work longer hours, move deadlines around, and multi-task.…

    • 1836 Words
    • 8 Pages
    Satisfactory Essays
  • Powerful Essays

    Schools of Management

    • 3115 Words
    • 10 Pages

    This method of management paid close attention to 'time and motion ' studies, where each worker is timed when performing a task, and then this provides the basis for the worker 's level of output per day (e.g. if it took a worker 2 minutes to perform a task, then this could be done 30 times per hour, and 240 times in an 8-hour day).…

    • 3115 Words
    • 10 Pages
    Powerful Essays

Related Topics