Preview

Network Analysis Advantages

Good Essays
Open Document
Open Document
475 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Network Analysis Advantages
NETWORK ANALYSIS ADVANTAGES

Network analysis can be used to assist the planning and management of complex projects. The following are some of the advantages that result from using the technique:
• To calculate the total project duration allows businesses to give accurate delivery dates. Customers may insist on a particular completion date and the critical time shows whether the firm can make this date or not.
• Calculating each activity allows the operations manager to order special equipment or materials needed for that task at the correct time. This ties the use of network analysis in with JIT strategies and assists in the control of cash flow and working capital.
• Calculating each activity provides a useful control tool for the operations manager. The manager will be able to see whether the project is up to schedule by checking the actual completion times of activities against the network.
• Knowing the critical path can be very useful. If there is a delay on a critical activity, there is no float because it is critical and the delay will, unless quick action is taken, put back the whole project. This could lead to expensive damage claims from the customer. By knowing the critical path, the operations manager can see which other activities need to be speeded up if one has been delayed. For instance, in the house-building example above, if E was delayed by two days due to bad weather or non-arrival of equipment, the operations manager would know that one of the following critical activities needs to be accelerated to catch up on time lost.
• The additional resources for speeding up a critical activity could come from the non-critical ones. To use the house-building example, if F is to be reduced to eight days to counter the delay, the resources of labour, materials and machinery could be taken, as they both have spare time. This will allow a better and more efficient use of the firm’s resources. This shows how the existence of float times and it allows



References: http://classof1.com/homework-help/statistics-homework-help

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project.…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    I a. Construct a network for the project. [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Due to schedule slipping and unforeseen circumstances that Joe was facing, his boss decided to give him “some “wiggle room” in the form of $30,000 of optional budget money”(Pinto, pg.315) that will solve short-term problem. Since he got extra $30,000 Joe can speed up the schedule tasks that need to be completed before the due date of the project. The long-term problem here is that the “delivery date for the project is fixed and cannot be altered without incurring substantial penalties.” (Pinto, pg.315) Due to limited time frame, extra money cannot help Joe’s team to complete all late schedule tasks and deliver project on time. To solve the long term Joe decided to crash the remaining activities with optional money to speed up project to its finish line.…

    • 429 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Business Studies Exam

    • 475 Words
    • 2 Pages

    This planning tool is actually used for sequencing and scheduling. As shown it determines the slowest or longest time the project can be completed and can save time with reducing the costs that will help XNH Pty Ltd a lot currently and in the near future.…

    • 475 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Sainsbury Operations

    • 2417 Words
    • 10 Pages

    Operations Management is very important in business operations since it forms the heart of the organisation by controlling the system of operation. Operations management plays a vital role because any operation requires a combination of merchandising, logistics, coordination and cost control skills to move products from production facilities to the consumer(2).…

    • 2417 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Beer Game Paper

    • 502 Words
    • 2 Pages

    There are transportation lead times in shipping the material from one location to another, and there is a production lead time at the factory. While material flows from upstream to downstream, information flows in the opposite direction through order placements. There is an order processing delay, or information lead time, between when an order is placed and when the order is received by the supplier. The players share a common objective to optimize the system-wide…

    • 502 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In many studies and reports, project successes tend to be measured against the prescribed schedule, cost and performance. In reality, project success measurement should be against projects constraints and the operational readiness status of the business environment. The combination of the two will assist in efficiently using the product or service as intended.…

    • 683 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management Models

    • 989 Words
    • 4 Pages

    A project defines a combination of interrelated activities that must be executed in a certain order before an entire task can be completed. Project management has evolved as a field of study, with the development of two analytical techniques for planning, scheduling, and controlling projects. These techniques are the project evaluation and review technique (PERT) and the critical path method (CPM). The purpose of this exercise is for the student to appreciate project planning issues and the application of PERT\CPM techniques. Please answer the following questions.…

    • 989 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Syllabus

    • 6241 Words
    • 25 Pages

    Course Description How do organizations such as financial institutions, health care, and manufacturing meet customer needs and stay consistent with their goals and values? How do organizations make tradeoff decisions with respect to quality, cost, and time? Operations Management provides tools and methods to optimally answer these questions in a global business world. Operations managers are primarily concerned with the design, procurement, production, and delivery of goods and services. They are responsible for the systematic planning, designing, operating, controlling and improving the various procurement, production, storage, and shipping processes involved from the time the product or service is designed till customer delivery occurs. The challenge for operations managers is to produce goods and services and deliver them in an efficient manner and in accordance with the business strategy of their company. Typically, this involves balancing the needs for satisfying customer demand, on-time delivery, lower costs, and higher quality. In this course you will learn the fundamentals of Operations Management, enhance your managerial insight and intuition, and improve your business decisions. 1…

    • 6241 Words
    • 25 Pages
    Satisfactory Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Capacity Management

    • 540 Words
    • 3 Pages

    Time may be a constraint where a customer has a particular required delivery date. In this situation, capacity managers often "plan backwards". In other words, they allocate the final stage (operation) of the production tasks to the period where delivery is required; the penultimate task one period…

    • 540 Words
    • 3 Pages
    Good Essays