Penny Black Case Study Summary
1) What are the core principles/characteristics of any project and why are they important?
(8 marks).
Ans:-The word project comes from the Latin word projectum from the Latin verb proicere, "before an action" which in turn comes from pro-, which denotes precedence, something that comes before something else in time. The word "project" thus actually originally meant "before an action".
A project is characterized as a community oriented endeavor, including research or outline that is precisely wanted to attain a specific point. It generally incorporates an arrangement of interrelated assignments that are gotten ready for execution over a settled time of time and inside specific prerequisites and restrictions, for example, cost, quality, execution,
…show more content…
Scope Statement

Ans:-The project in the case study is for ‘Grabbit and Scarper & Sons Limited’ that has appointed Penny Black to join the team and in the first instance, to take over responsibility for the project management of a special project in the North East, with a view to then managing a new plant in the USA within the next 5 years. In the project Penny Black has to look for upgrade of plant that includes physical assets, mainly pumps and compressors and complete in 6 months
An in depth study and analysis of the case study identifies the following activities and deliverables in scope:-
 Tender for machinery– tenders to three approved pump manufacturers and installers, and three different companies specializing in compressors
 Identification of Tender conditions:-An analysis on clauses to be placed in the tender like quote, post installation services, standing charges is important to safeguard company’s
…show more content…
It is helpful placing the correct orders in tender

3) What difference would it have made if Penny Black had plotted out a full project Gantt chart and critical path? (6 marks).

Gantt charts could have helped Penny Black to Avoid Completion Confusion by keeping tender orders on track by providing a visual overview of milestones and other key dates, offering a more understandable and memorable method of maintaining deliverables to be tracked on a daily, weekly, monthly basis.
There would have been better chance of keeping project costs within budget while also better assuring on-time completion.
With the help of critical path she could have taken into consideration the requirements well in advance to complete a project in the most efficient way possible and determine the duration and estimate exact time and cost of the project. It could have enabled her to minimize the project length by monitoring the critical path by quick decision making to address the issue quickly

4) What method(s) would you employ for cost management and why? (4

You May Also Find These Documents Helpful

  • Satisfactory Essays

    •Project definition and planning: The scope of the project will need an outline so the work which needs to be performed is available. Prioritizing, budgets and timelines are in this phase as well.…

    • 2364 Words
    • 8 Pages
    Satisfactory Essays
  • Good Essays

    case study 2 tlmt 313

    • 951 Words
    • 3 Pages

    Fauquier Gas Company, is one of the nation’s 440 gas companies, served an area where land use was changing from agricultural to residential and commercial. The company is beginning a new project that consist of having 3 ½ miles of lines ready to be hooked up by September. This is another one of the demands that Fauquier have on their hands not including the additional 10 lines that they plan on starting for next project. It takes great deal of engineers and contractors and constructions workers to meet this deadline, not to include precise planning. Mr. Clive Byers is the construction project manager, Mr. Charlie Buck is the design superintendent, Pat Wilson is design engineer, Sam Law is project engineer, and Mr. Bill Murphy is the manager of supply management. All of these individuals are under management of the vice president of operations for the company. These individuals play a huge role in meeting all requirements and specifications for this project. In order to meet all the deadlines into building this project all parties involved have to communicate effectively. Mr. Murphy is responsible for ensuring all the supplies that goes into ordering is placed and delivered in a timely manner.…

    • 951 Words
    • 3 Pages
    Good Essays
  • Good Essays

    In this case study presented by Hood (n.d.), Fauquier Gas Company is up against a timeline to supply a new construction project in the works where agricultural land was being developed into residential and commercial use. Fauquier Gas Company is looking for supplier to help with building of 3 ½ miles of new gas pipe that will go online by beginning of September. The manager of supply management Mr. Murphy is having trouble getting any purchasing request for the new pipeline from Mr. Charlie Buck and the specifications from the design team to know what he needs to order. This project is to be complete in the next five months to meet the new gasoline project. The vice-president of operations for Fauquier Gas Company has the management control over the supply organization including Mr. Murphy, construction project manager Clive Byers, design engineer Pat Wilson, and design Superintendent Charlie Buck. Mr. Murphy faced many logistical and supply problems from the very beginning of this project. Lead-time is essential for design team getting all the information on the new pipe to the Mr. Murphy so he can get the much need specification out to the need vendors to supply the correct materials for the upcoming project that need to finish by September. The biggest problem that Mr. Murphy came across was the new specifications for the new pipe were the wall thickness and length was different from previous purchases which could hurt in finding new vendor or seeing if older vendor can meet specifications on the new pipe. Pat Wilson informed Mr. Murphy the reason for the different specifications was the operation of the line would be governed by less stringent specifications and using 57-foot-length pipe versus “random double normal” (40 feet plus or minus 5 feet) would reduce welding costs. The coating for the pipe was also another problem that Mr. Murphy faced as no of team was communicating with each other on how to…

    • 901 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Stanhope Project

    • 1020 Words
    • 5 Pages

    Jim Wickes was in charge of recommending projects to Steve White the executive Vice President for ABI. This case involves the decision of whether or not to move forward in a flexible manufacturing project for Stanhope Iowa. Ann Williamson composed a project that had large risks and large rewards. The decision of whether to accept the project posed large financial issues for the company. A large tractor company “Big Red” was entertaining the idea of negotiating a contract for a single source for all of their diesel engines. Recently the Japanese tractor companies had become very competitive. ABI could lose market share if this decision is handled poorly.…

    • 1020 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    “Gantt charts are useful for both scheduling and tracking the activities of systems implementation projects because actual progress can be indicated directly on the Gantt chart and contrasted with the planned progress. Gantt charts are straightforward, easy to understand, and can be used with PERT to compare…

    • 911 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Q1) Discuss the benefits to Balfour Beatty of using critical path analysis in order to plan its construction projects. (15 marks)…

    • 711 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Fauquier Gas Company is slated to begin a new project to turn an area once used for agricultural work into a residential and commercial property. This means that new gas lines must be installed. In January, Mr. Murphy overheard Mr. Byers, the project manager, discussing the requirement to add 3.5 miles of new gas lines slated to begin in June with an estimated completion date of September (3 Months). Having worked with the procurement of gas lines before, Mr. Murphy knew that the mills needed substantial lead times in order to accommodate Fauquier Gas Company's timeline. Mr. Byers advised Mr. Murphy the purchase request would be sent as soon as the design engineer was finished with the specifications and the project engineer approved it, both work areas fall under the vice-president of operations.…

    • 1547 Words
    • 7 Pages
    Better Essays
  • Good Essays

    Writter

    • 610 Words
    • 3 Pages

    Unlike other functions carried out in the daily operations of an organization, a project is a temporary endeavor undertaken to create a unique product, service, or result, further some specific characteristics that differentiate projects from other functions of an organization are identified by the length that it takes to complete the job or project. It is important to understand that A project is short lived, meaning that it must be finished within a certain time frame and fit within a specific budget while the organizational functions operate continuously and have the ability to continue throughout the lifetime or until the organization stops its operations all together. Five examples of work that is not considered to be a project are listed below, I have selected the below with the understanding that non project work is considered routine work.…

    • 610 Words
    • 3 Pages
    Good Essays
  • Better Essays

    Contract Disputes

    • 1248 Words
    • 5 Pages

    “CONTRACT DISPUTES REACH 15-YEAR HIGH”, was the heading of an article published, December 1, 2010 in the Government Executive. The heading in itself tells us that the government is doing more and more business by contract and as a result contractors who are lobbying for government business have become more aware of their rights to file disputes when it involves a loss of potential business. Because of this increase in disputes, the government must have a method of terminating contracts without suffering the financial liabilities that could result in millions and millions of dollars going to incomplete contracts and rebids to acquire a contractor for completion of unfinished contracts. This method of termination is known as a Default Clause which will be covered later in this paper. First we will look at a case that involves a contract dispute. The GAO file number: B-215789 which involves J.C. Hester Company, Inc who was awarded contract number: F34650-81-C-0158 with the Department of the Air Force. My reason for choosing this dispute case was because it requires that the individual look at all aspects of the case in reference to Disputes. Usually dispute cases depend on more than one aspect of the FAR. This case shows that not only the contractor but the contracting officer should pay strict attention to the reasons for the dispute. In this case knowledge of the Bids Protest Process area of the FAR is also required to determine if the recommendation by the Comptroller General was indeed valid and fair.…

    • 1248 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is your opinion on the potential for the project to be completed on time?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    • Requirements must also be clearly defined in the tender offer. Specifications must be independently checked before final issue to ensure they can be clearly understood and so as not to leave room for suppliers to define key terms after the tender is awarded.…

    • 909 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    1. PROJECT – a set of activities directed toward a unique goal, usually large scale, with a limited time frame.…

    • 253 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Pert/Cpm

    • 364 Words
    • 2 Pages

    Graphical displays such as gantt-charts usually make the information easy to identify; and we can easily use it for tracking cost, schedule and performance.…

    • 364 Words
    • 2 Pages
    Good Essays
  • Good Essays

    A project is a specific task that has a beginning and an end. Project management is used for defining the process of executing a project in a systematic manner.…

    • 4790 Words
    • 20 Pages
    Good Essays
  • Powerful Essays

    Project Specialist

    • 2642 Words
    • 11 Pages

    Projects get talked about quite a lot these days. Per Dennis (Lock, 2007)projects date back before the 1900’s when project planning tools like the Gantt charts were in use. In the1950s when computer use became pretty expansive, project planning and scheduling tools were developed. Projects differ in size, scope, cost and time. There are now big international projects requiring millions of dollars to implement over a number of years to small projects taking days or months to conclude. As such, a project can be defined as a set of unique and coordinated activities undertaken to deliver a desired result in a given specified timeframe ( (Harvey, 2010). Projects are very important in the development of a country, organization, and even individuals. Effective Project Management is a catalyst essential towards the creation of change that enhances the ability to do things more efficiently and effectively.…

    • 2642 Words
    • 11 Pages
    Powerful Essays