Preview

Section 00199 2008 Standards For Construction

Good Essays
Open Document
Open Document
556 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Section 00199 2008 Standards For Construction
Section 00199 2008 Standard Specifications for Construction
Disagreements, Protests, and Claims (Summary)
00199.10 Procedure for Resolving Disagreements - When disagreements arise between the agency and contractor concerning additional compensation and or additional contract time and compensation, the contractor will first attempt to come to a resolution through the Engineer of all the issues. If a satisfactory resolution cannot be reached between the contractor and engineer, the contractor will follow the protest procedures in 00199.20.
00199.20 Protest Procedure – If a contractor disagrees with work required in a change order or other written or spoken order from the engineer in the contractor’s opinion entitles or would entitle the contractor to additional compensation, the contract will complete all of the following to pursue a protest and preserve it claim. The contractor is required to give oral notice of protest to the engineer, file written notice of protest with the engineer within seven days after receiving the protest order.
…show more content…
At any time during the of the project, but not later than 15 calendar days following the date of the second notification, the contractor will submit to the engineer claims for additional compensation or additional combination of compensation and contract time to the specified contract. For claims to be considered the contractor must submit an executive summary; copies of contract specification that support the contractor’s claim, theory of entitlement, itemized list of claim amounts, additional contract time request, and actual expense

You May Also Find These Documents Helpful

  • Good Essays

    It seems as though neither ReadyPro or Bengali Gas Pipeline Company held up their end of the bargain by issuing timely paychecks to Janice. Neither company took the necessary measures to keep Janice happy, even though her requests were completely justified. Bengali Gas Pipeline company also reduced the amount of reimbursements Janice was contracted to receive, even though they said they were unwilling to make any changes to the existing contract. Bengali Gas Pipeline Company violated their own contract by reducing the amount of reimbursements Janice was supposed to receive.…

    • 748 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Netw310 Week #4

    • 313 Words
    • 2 Pages

    Once the permit is issued, the permittee will have to give the Department of Engineering Services a minimum notice of 48 hours prior to commencing work.…

    • 313 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Defense Construction declared that it was just a clarification and accepted the bid. Analysis The appellant used the Ron Engineering, Supra case to conclude that there was a contracted formed between the owner and each of the tenderers. The contract was Contract A. Since there was a formal contract introduced, the breach by Sorochan Enterprises Ltd. for introducing a stipulation for their bid, in the form of an additional charge, and because Defense Construction accepted this non-compliant bid, the Contract A between the other tenderers was broken.…

    • 1347 Words
    • 6 Pages
    Better Essays
  • Good Essays

    First, a pre-complaint notice must be filed with the CCB. The pre-complaint notice that is sent to the contractor must have all of the following information date; contractor’s name, contractor’s address, a statement that the plaintiff plans to file a complaint with the CCB, and the plaintiff’s name. The pre-complaint must be sent to the contractors name and address that is on record with the CCB. Moreover, the pre-complaint must be sent certified mail to the contractor. At this time, the contractor can respond and correct the items of issue in the pre-complaint (Oregon Construction Contractors Board, n.d.).…

    • 649 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Asp Cacf Case Study

    • 236 Words
    • 1 Page

    In your grievance filed at ASP-CACF, you claim you received an unsatisfactory evaluation for the month of November causing you to lose pay. You further assert that the disciplinary ticket you were issued was dismissed. Your resolution is to have the evaluation changed and to receive your back pay.…

    • 236 Words
    • 1 Page
    Satisfactory Essays
  • Powerful Essays

    When a procuring agency fails to adhere to the regulations and/or the terms listed within the solicitation, a bid protest may be filed (Nacke & Ralston 2011). A bid protest is a tool that a contractor can use to legally contest the process or result of a government contract award. In order to file a protest, one must be considered an interested party, meaning they are an offeror or prospective offeror who would be financially affected by either the award or the non-award of the contract. There are three different types of protests available to contractors. Each has differing procedures but they share the main requirement; In order to win, they must provide supporting information which would prove that they have been prejudiced by the government agency. The two most common forms of bid protest are the agency-level protest and the Government Accountability Office (“Bid Protests,” 2010).…

    • 4029 Words
    • 17 Pages
    Powerful Essays
  • Satisfactory Essays

    The site visits for the unit 2 assignment started whilst general civil works were taken place, this involve foundation works for tanks, buildings, turbine rooms, paving and culverts for underground piping, etc. There were various types of work activities that range from Shallow to Deep foundations. Refer to photos in appendix 1 for further clarification.…

    • 456 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    In the future, if Citizen-Schwarz AG continues to change their original contract requirements there needs to be sign offs from both Span Systems and Citizen-Schwarz AG directors. Prior to Span Systems' director signing off Citizen-Schwarz AG's request, a panel of senior programmers at Span Systems needs to approve the request, so programming changes can be adequately evaluated. Span System programmers want to be assured that timetables and schedules can still be met within the agreed upon contract. If Citizen-Schwarz AG's request requires more time to meet the deliverables of the project then Span Systems and Citizen-Schwarz AG need to exercise the ‘Requirement Change' clause within the contract. This clause is meant to formalize a change and suppose to notify and bring in upper management from both sides to handle a change request by following the Information Technology Project Methodology Standard. This clause is not written to handle out of the ordinary requests. This clause needs to be able to handle difficult requests and effectively document a procedure that can hold both sides accountable for changes made to the original contract. This clause also needs to be streamlined, so that both parties can act quickly upon agreed changes to the contract. It would be best to amend a clause to the current contract that is specially written to handle requirement changes throughout the project. This clause should document the process to effectively make difficult change request. This process should also require sign offs from project directors from both companies. In addition, each change request needs to be a legal contract that carefully documents how the scope of the project changes with each request. Each request absolutely needs to document how the timetables and schedules will be affected through the continuation of the project.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Nvq3

    • 257 Words
    • 2 Pages

    B4; describe the procedure to follow if you wanted to raise a grievance at work. you may describe this in writing or produce a flow chart or diagram.…

    • 257 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    HEALTH AND SAFETY HSC037

    • 2460 Words
    • 8 Pages

    1. Explain own role in supporting others to follow practices that reduce the spread of infection…

    • 2460 Words
    • 8 Pages
    Better Essays
  • Satisfactory Essays

    The Dispute Settlement Mechanism (DSM) of the WTO constitutes the guarantee of the legal structure arising from the WTO Agreements. This mechanism is only applied to trade disputes between WTO Member states and arising from government policies but the disputes between person and firms are out of the scope of DSM. The main purpose of the mechanism is to ensure that WTO Members act in accordance with the WTO Agreement, to protect the rights and obligations of the Members under the WTO Agreements and to ensure reliability and predictability of the multilateral trading system. DSM can only be applied to the disputes stemming from the Agreements listed in Appendix 1 to the DSU. The mechanism which is automatic, obligatory and has appeal; compensation and retaliation mechanisms functions quite effectively.…

    • 1398 Words
    • 8 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In a work place, if a complaint is issued towards you, the procedure you must take in order to resolve the complaint is:…

    • 1005 Words
    • 5 Pages
    Satisfactory Essays
  • Good Essays

    managing people performance

    • 3284 Words
    • 12 Pages

    Your up-line manager has called you into the office to discuss a situation they have only aware of. One of your major customers, Organization X, has expressed dissatisfaction with service provided by your organization. You have an ongoing contract to supply this customer goods until the end of the year. At this time the contract will be re-negotiated. Apparently Organization X has expressed their dissatisfaction on a number of previous occasions, but there has been no real improvement. As a result of the poor service and the problems with supply manager of Organization X has strongly suggested that the contract will not be extended fact, be offered to another organization.…

    • 3284 Words
    • 12 Pages
    Good Essays
  • Good Essays

    Ilm 3 Communication

    • 785 Words
    • 4 Pages

    We both took notes throughout the discussion, and I wrote these up afterwards. I then used them as the basis of an e-mail to the contractor, which confirmed what I believed we had agreed, for him to amend or agree.…

    • 785 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    National Building Code

    • 2299 Words
    • 10 Pages

    2. Permits supplementary to a Building Permit shall be applied for and issued by the building official. These include Ancillary and the Accessory Permits.…

    • 2299 Words
    • 10 Pages
    Powerful Essays