Preview

managing projects

Powerful Essays
Open Document
Open Document
3062 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
managing projects
MANAGING PROJECTS

Name:

Course:
Professor:
Institution:
City and state:
Date:

1. Draw the network diagram (use activity on the node)

2. Explain how you determined the timing of activities and the total float.

From the diagram above, the ES or earliest start time is zero for activity A. Therefore, ES equals the EF or earliest finish time of the predecessor. An example can be from the diagram above as ES of C activity is EF of activity B i.e. 9 days. Earliest finish time is computed when the duration of any activity is added to the earliest start time. The equation will be:
Earliest finish time = Earliest start time + Duration
For example, the above equation can be used for calculating EFT for activity C.
EFT of C = 9 days + 10 days
It is important to note that any activity with the longest duration is specified as the critical activity (Baker 2001). From the activities of SamMax Ltd, activity C has the longest duration i.e. 10 days as compared to other activities which have 9, 8 and 6 days of activities D, E and F, accordingly.
The latest start time is computed by adding float to latest start time of the critical activity (Anon 2007). The equation for this scenario is:
Latest start time = Latest start time or EST of the critical activity + total float
The equation can be used for activity D where LST of critical activity C is 9 days plus total float of activity D i.e. 1 day. The addition results in 10 days.
The latest finish time can be calculated as the addition of duration to latest start time of activity and the equation can be written as under:
Latest finish time = Latest start time + Duration
The above equation can be used in calculating the LFT of activity E i.e. EFT of E is 11 days and the duration is 8 days. Therefore, LFT for this activity is 19 days.
The total float is calculated by deducting EST or earliest start time and duration from latest finish time (Furman 2011). The example can be



References: Holland and Holland Enterprises Ltd. 2011, Successful Project Management. [Online] Available at: http://www.successful-project-management.com/network-diagram.html [Accessed 17 December 2013].

You May Also Find These Documents Helpful

  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    Determine each of the following: Task Earliest Start Latest Start Earliest Finish Latest Finish Slack A 0 6.5 3 9.5 6.5 B 0 0 7 7 0 CRITICAL C 3 9.5 7.5 14 6.5 D 7 7.5 18.5 19 0.5…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    Filgrastim Research Paper

    • 944 Words
    • 4 Pages

    Time: Route is IV or SubQ. Onset is unknown, Peak is unknown, duration 4 days…

    • 944 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    What is the slack time (float) for activity A? (1 points) d) What is the slack time (float) for activity D? (1 points) e) What is the slack time (float) for activity E?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    [pic] Slack or Float = LF – EF or LST – EST Activities on the critical path have zero slack/float. b. Calculate the scheduled completion time and identify the critical path(s). Scheduled…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    3) Refer to the figure. What is the slack time, in days, associated with activity E?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    It is important that the constraints above refer to performance averaged across the two day…

    • 958 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    c. Often two or more activities can start simultaneously or a lag takes place between the start of one activity after an earlier activity has commenced. An example would be in a project when one activity can be labeled a ‘burst point’ to multiple successor activities.…

    • 310 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    operation management

    • 252 Words
    • 1 Page

    To conclude, we cut activity T by 2 weeks. The project can be completed in 14 weeks.…

    • 252 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    In the question, it defined date 1 as the first trading day of the study period. Date 0 which is one day before the first trading day Date 1. First of all, using excel to set up the time index column to arrange the date of the trading day. The range of the data is from date 0 to 1087.…

    • 1062 Words
    • 5 Pages
    Satisfactory Essays
  • Powerful Essays

    Mgt150 Assignment 1

    • 970 Words
    • 4 Pages

    University of Management and Technology MGT 150 Project Management Assignment 1 Bottom-up cost estimating exercise (Module 3, pp. 19-20) 1.0 Research 1.1 Birdhouse Book…………………………………………………. …… $ 30.00 1.2 Jimmy’s time to read up on birdhouses…………………….… …… $ 4.00 1.3 Dad’s time………………………………………………………. ….… $ 80.00 2.0 Materials acquired 2.1 Lumber…………………………………………………………..…

    • 970 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    Dragonfly case study

    • 1041 Words
    • 5 Pages

    3. The Earliest Start (ES) and Earliest Finish (EF) and Latest Start (LS) and Latest Finish (LF) times are calculated using Forward Pass and Backward Pass Algorithm.…

    • 1041 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    hour. The goal of wave scheduling is to begin and end each hour on time.…

    • 127 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Astable Multivibrator

    • 439 Words
    • 2 Pages

    The circuit diagram for the astable multivibrator using IC 555 is shown here. The astable multivibrator generates a square wave, the period…

    • 439 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Activity 7, Guest list. Add 3 days for the flu. Now duration is 7 days.…

    • 423 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Tastee Snax Cookies

    • 2554 Words
    • 11 Pages

    5 4 RESULTS ...................................................................................................................................................... 5 5 WHAT-IF ANALYSIS ................................................................................................................................ 6 6 OVERALL RECOMMENDATIONS .......................................................................................................... 7 7 APPENDIX ................................................................................................................................................... 8 7.1 TABLE 1: ACTIVITIES WITH CRASHED TIME AND ADDITIONAL COSTS .......................................................... 8 7.2 TABLE 2: CPM DEADLINE INPUT 46,47 & 48 WEEKS................................................................................... 9 7.3 TABLE 3: CPM DEADLINE OUTPUT 48 WEEKS.............................................................................................…

    • 2554 Words
    • 11 Pages
    Powerful Essays