Preview

Dependencies and Network Diagram

Better Essays
Open Document
Open Document
1125 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Dependencies and Network Diagram
Dependencies and Network Diagram
The network diagram is a schematic representation showing the sequence and relationship/ dependency of the tasks along with their duration. All the tasks, except the first and the last, are linked with at least one predecessor and successor to have a proper sequence of work. This logical dependency between the tasks will determine afterwards the duration of the project. There are four types of dependencies which define the relation between pair tasks Finish-to-start (FS- the second task ‘successor’ can’t begin until the first ’predecessor’ is completed), Finish-to-finish (FF- the completion of the successor depends on the completion of its predecessor), Start-to-start (SS- the start of the successor depends on the start of its predecessor), Start-to-finish (SF- the finish of the successor depends on the start of its predecessor).

Critical Path
However the duration of the project is meaningless without identifying what is driving the project, why the project takes so long, what possible action is required to shorten the duration or what possible risk may extend the project...
Among the set of activities interconnected on the diagram; there is always one longest duration path from start to end of the project travelling through the network, Carmichael D. (2006, p.51). This longest path is also known as a critical path driving the project duration and all tasks falling on this path are called critical activities. Any delay which occurs on these critical activities will delay the project completion time as well. The critical path analysis is carried out in three steps. The first step consists of forward pass which calculates the early schedule (earliest start time and earliest finish time of a task).
If a schedule activity has two or more predecessors, its early start is governed by the early finish time of the preceding activities whichever is maximum.
The second step is the backward pass which calculates the late schedule

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    a. The most common type of logical sequencing between tasks is referred to as the Finish to Start Relationship. An example of a delay would be if three activities are linked in a serial path, activity number 3 cannot begin until the scheduled task from activity number 2 is completed in full.…

    • 310 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    In the book of John, the author said, “We must work the works of him who sent me while it is day; night is coming, when no one can work” (John 9:4, ESV). In biblical worldview, many scriptures identify time and work related approaches. Project duration is an important aspect of the project. Klansek, U., & Psunder, M. (2008) stated, “Each activity within project network is characterized by its precedence relations, duration, and resource requirements”. After doing Part 1 of the Red Zuma project, I realized that many factors can affect the project duration. For example, if the resources are overallocated they can get leveled. When resources get leveled within the slack it can cause changes in areas such as the critical path and duration. It is…

    • 317 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project.…

    • 605 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    The network diagram is a logically schematic display provides graphical view for the project details like the tasks required to be performed, the relations between them and the duration’s estimations for the task itself and for the entire project including the earliest time to beginning the work in a every task the earliest predicted finishing date of the project. Network diagrams used for detailed planning, analyzing scheduling in project implementation and as a control tool in the monitoring and control phase. Two methods used to build the network diagram task-on-the-arrow (TOA) method and the recently one called the task-on-the-node (TON) method, or, the precedence diagramming method (PDM).…

    • 941 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Book Report

    • 683 Words
    • 3 Pages

    Critical path is the one that determines the shortest time to complete a project, which assumes low uncertainty and does not consider resource dependencies.…

    • 683 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    As the activity B does not located on critical path, therefore the completion time no change even its shorten one week. For the activity G which is located on both critical path 2(ACFGI) and 3(ADFGI), therefore it is key activity for the project and has to shorten. Due to activity C and D is location on critical path 2(ACFGI) and 3(ADFGI) respectively, if only shorten activity C or D then another one become critical path, therefore both activity C and D have to shorten one week at same time. Conclusion, I would choose activity C, D and G to shorten the completion time as above reasons.…

    • 427 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    3. Suppose that activity AD were delayed by 2 weeks (takes 8 weeks versus 6). What is the new project completion time and critical path?…

    • 337 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Pearl diving

    • 403 Words
    • 2 Pages

    Defining the critical path is also an important aspect of project scheduling. It is basically the longest path through a project. It determines the earliest possible completion of the work. The critical path is carefully managed because if critical path is not followed properly then it would detour the whole project.…

    • 403 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    36. A must finish before B can start, both A and C must finish before D can start…

    • 259 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A critical path analysis will be undertaken to produce a network diagram showing the earliest and late times and a total float for each activity. This will help to provide the following criteria:…

    • 704 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The Network Diagram

    • 540 Words
    • 3 Pages

    To determine timing of activities in the network diagram the following calculations were done for each node: Earliest Start-(ES), Earliest Finish-(EF), Latest Start-(LS) and Latest Finish-(LF).…

    • 540 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 676 Words
    • 3 Pages

    Any project must be well planned especially if a number of people and activities will be involved. It is the task of the project management to ensure that various tasks required in the project are completed in time. Operational researchers developed a method of scheduling complex projects shortly after the Second World War. This scheduling is called network analysis and is usually known as Critical Path Analysis (CPA).…

    • 676 Words
    • 3 Pages
    Good Essays